Today one of the SAP Training students asked how to view Factory Calendar in SAP when discussing Scheduling in SAP ?
Use the following Menu path
[ spro -> IMG -> SAP Netweaver -> General Settings -> Maintain Factory Calendar ]
Select “Factory Calendar” and then click the view button. Select the SAP factory calendar you wanted to view ( in this case “US Factory Calendar” ) and then click on the Definition button.
Here you can see the definition of the US Factory Calendar.
The holidays associated with that calendar can be viewed using the SAP Holiday Calendar ID “US” . As usual , you need SAP Access to practice this. This is important for SAP MM Training, SAP PP Training and other SAP Modules as well.
Question 1 : Create a Custom Factory Calendar Zx valid from 2000 to 2020
Question 2 : Can you create a Factory Calendar without specifying the Holiday Calendar ?
Question 3 : Make the working days in the calendar Zx as Monday through Saturday.

Answers:
Question 1 : Create a Custom Factory Calendar Zx valid from 2000 to 2020
Ans. Created VR
Question 2 : Can you create a Factory Calendar without specifying the Holiday Calendar ?
Ans.No
Question 3 : Make the working days in the calendar Zx as Monday through Saturday.
Ans: Done
1)zy
2) NO
3)zy saved as per requirements
1) ZZ created, validity date would only allow from 2010-2014
2) No
3) Done
Question 1 : Create a Custom Factory Calendar Zx valid from 2000 to 2020
A. Calendar ZR created.
Question 2 : Can you create a Factory Calendar without specifying the Holiday Calendar ?
A. No.
Question 3 : Make the working days in the calendar Zx as Monday through Saturday.
A. Done.